Applications

Typical Application Methods

 

Application Method #1 - Mix-In Application

 

To Address Permanent Heavy Weight Traffic Area Requirements for the Following:

 

 

  1. Grade, contour and compact the soil to final elevations.
  2. Till soil to the specified depth of treatment with a roto-tiller (i.e. 2 inches)
  3. Spray-apply the required amount of properly diluted PolyPavement onto the loose soil.
  4. Till the soil again to thoroughly mix soil and PolyPavement.
  5. Re-compact the soil with a steel drum roller.
  6. Spray-apply the required amount of properly diluted PolyPavement onto the compact soil surface.
  7. Allow the soil to dry.

 

Application Method #2 - Spray-On Application (Traffic)

 

To Address Temporary Light Weight Traffic Area Requirements for the Following:

 

 

  1. Grade, contour and compact the soil to final elevations.
  2. Spray-apply the required amount of properly diluted PolyPavement onto the compact soil surface.
  3. Do not allow the soil to dry.
  4. Spray-apply the required amount of properly diluted PolyPavement onto the treated soil surface.
  5. Allow the soil to dry.

 

Application Method #3 - Spray-On Application (Non-Traffic)

 

To Address Short-Term to Long-Term Non-Traffic Area Requirements for the Following:

 

 

  1. Spray-apply the required amount of properly diluted PolyPavement onto the existing soil.
  2. Do not allow the soil to dry.
  3. Spray-apply the required amount of properly diluted PolyPavement onto the existing soil.
  4. Allow the soil to dry.

 

*DILUTION RATIOS: spread rates and depth of treatment vary depending on factors such as desired end results and specified performance criteria. PolyPavement Technical Department provides detailed application instructions in accordance with project performance specifications.

 

SIMPLIFIED:

 

Application Method #1 - For Permanent Traffic Areas Mix PolyPavement™ Into the Soil, Compact the Soil

 

Application Method #2 - For Temporary Traffic Areas Spray PolyPavement™ Onto Compact Soil, Let It Dry

 

Application Method #3 - For Non-Traffic Areas Spray PolyPavement™ Onto Existing Soil